Foundation Blocks
The foundation blocks have been completed and are ready for the gravel backfill.
-
Footings Poured
The footings have been poured and the foundation blocks will soon be laid.
-
Dormitory Footers & Access Road
E. Carroll Mann Contractors is digging the footings of the two dormitories and Glover Construction is on site to complete the graveling of the entry road and parking lot. Also, they installed and graveled the access road to the dorm construction site. We praise the Lord for those who are partnering with us to see CWS become a reality. This is a great day!
-
Surveying the access road
Chandler Land Surveying is on site to stake the access road to the two dormitories under construction as well as staking the location of utility transformers.
-
Clear Skies
In mid-January, the rain began. As you may know, it rained and it snowed and then it rained and snowed some more (see the result below). As the ground has finally dried in mid-February, we are able to take advantage of the nice weather and there is much activity taking place on the CWS property.
-
Weather Delays
Due to a projected major winter storm, we will delay our mailing of summer registration forms by one week. The registration forms will be placed in the mail Saturday, February 6, 2010. The online registration form will be available for download at noon on Monday, February 8. We apologize for any inconvenience and appreciate your patience in this matter.
-
Buildin Permits Obtained
The building permits have been obtained and we are ready to begin construction. This is an exciting time as we have waited several years to see buildings spring up on the CWS property!
-